Mangdechhu Hydroelectric Project.

posted Mar 19, 2013, 1:09 AM by Tashi Wangyel

Engineering, Design & Contracts Department in counterpart with the Development & Construction Department and Transmission Department has successfully completed the walk on survey of following two numbers 400 kV D/C Transmission Lines from Mangdechhu Hydroelectric Project power house pothead (Trongsa) to proposed 400 kV Jigmeling Substation (Sarpang) via proposed 400 kV pooling Substation at Goling (Zhemgang).


1) Proposed Mangdechhu – Goling 400 kV D/C Transmission Line A = 37.05 Km
2) Proposed Goling – Jigmeling 400 kV D/C Transmission Line A = 42.76 Km
TOTAL (I) = 79.81 Km

3) Proposed Mangdechhu – Goling 400 kV D/C Transmission Line B = 37.33 Km
4) Proposed Goling – Jigmeling 400 kV D/C Transmission Line B = 42.45 Km
TOTAL (II) = 79.78 Km

GRAND TOTAL (I) + (II) = 159.59 Km

 (Courtesy: BPC, Posted on Dec 30, 2011 in Announcements)